The short answer
On most construction contracts in England, money moves through a fixed sequence. First the payee applies for payment. Then the payer issues a payment notice. If the payer wants to pay less, it must serve a pay less notice in time. Payment is then due by the final date for payment. Miss a notice and the sum stated in the application (or the payee's own notice) can become the amount you have to pay. Separately, VAT and CIS follow their own rules. Directors who treat the payment cycle, VAT and CIS as one process have better cash flow and fewer disputes.
1. The payment sequence under the Construction Act
The Housing Grants, Construction and Regeneration Act 1996, as amended in 2011, sets the rules. When a contract does not set out compliant payment terms, the Scheme for Construction Contracts fills the gap.
- Payment due date: set by the contract (or the Scheme).
- Payment notice: under the Scheme, the payer must give it no later than five days after the payment due date. It states the sum the payer considers due and how it was calculated.
- Pay less notice: if the payer intends to pay less than the notified sum, it must give notice no later than seven days before the final date for payment under the Scheme, unless the contract sets another period.
- Final date for payment: under the Scheme, 17 days after the payment due date if the contract is silent.
Why it matters to a £1m+ contractor: you are usually the payer to subcontractors and the payee to your client at the same time. A late pay less notice on your supply chain can lock you into paying a sum you dispute. A late notice from your client can strengthen your own claim.
2. Valuations: where the commercial and finance teams must meet
The valuation is the commercial assessment of work done. The notices are the legal record of it. Good practice for directors:
- Diary the due date, payment notice deadline, pay less deadline and final date for every live subcontract package each month.
- Make sure the person who signs off the valuation is not the only person who knows the deadlines.
- Keep the calculation behind every notice. The notice should show the basis on which the sum was calculated.
3. VAT: an application is not an invoice
For contracts with periodic or stage payments, HMRC's guidance says the VAT tax point is generally the earlier of receiving payment or issuing a VAT invoice. An application for payment that is only a request for payment, and is clearly marked "This is not a VAT invoice", does not create a tax point on its own. If your applications look like VAT invoices, you could account for VAT before you are paid. Where the domestic reverse charge applies (VAT-registered parties, payments reported under CIS), the customer accounts for the VAT. Your paperwork must say so.
4. CIS: deductions follow the payment, not the application
CIS deductions are made when a contractor pays a subcontractor, on the labour element. They are reported on the monthly return for the tax month in which the payment was made. A dispute that delays or reduces payment therefore moves the deduction and the return. Your CIS statements must match what was actually paid, not what was applied for.
5. Retentions
Retentions held under a contract follow the same notice rules when they fall due. For VAT, HMRC treats retention as part of the contract price. The tax point for the retained amount is normally when it is paid or a VAT invoice is issued, whichever is earlier. See our guide: construction retentions, cash flow and VAT tax points.
Three actions for next week
- List every live package and check that its payment and pay less deadlines are in someone's diary.
- Check that your application template says "This is not a VAT invoice" where that is intended.
- Reconcile last month's CIS return to payments actually made, not to applications.
FAQ
Is an application for payment a VAT invoice?
Not if it is only a request for payment and is marked as not being a VAT invoice. For stage-payment contracts, the tax point is generally the earlier of payment received or a VAT invoice issued.
What happens if a payer misses the pay less notice deadline?
In general, the payer must pay the notified sum by the final date for payment and cannot withhold part of it for that cycle. Take legal advice on any specific dispute.
When is CIS deducted on a disputed application?
When the payment is actually made, on the labour element of what is paid. It is reported on that tax month's return.
How we help: our CIS accountants for contractors reconcile notices, payments, CIS returns and VAT each month for South Yorkshire contractors over £1m turnover.
This guide explains finance and tax effects. It is not legal advice on contract disputes.
Sources
- Housing Grants, Construction and Regeneration Act 1996, ss.110A–111 (legislation.gov.uk)
- The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II paras 8–10 (legislation.gov.uk)
- HMRC VAT Time of Supply manual VATTOS9110 and VATTOS9165 (gov.uk)
- HMRC VAT Notice 708 (retention payments) and the VAT domestic reverse charge technical guide (gov.uk)